Proposed MahagonaWewa is an abandoned tank denoted by the Coordinate S/1 (2.0 X 8.6) and situated in Dambulla Divisional secretary division of Matale district. Total Estimated cost is Rs. 70 million the amount of revised estimated is Rs. 260 million due to the variations are encountered.

84.80 million have been utilized up to the end July 2016. Cumulative Physical Progress of the project was 56 %.

Physical Progress was achieved for following items at the end of July,

  1. Construction of main bund – 95%
  2. Construction of Sluice – 85%
  3. Construction of Spillway – 8%
  4. Construction of Rip rap – 20%

56